
![]() |
Consented development |
We plan to redevelop the existing site. There will be a new remote well site for up to six wells and 1.2km high pressure flow line to the main site.
There will be a 4.4k pipeline (24” in diameter) that leads to an above ground installation (there will be an underground connection point).
The proposed development comprises:
The purposes of the four elements of the project are to:
The gas is injected and extracted as follows:
Please click on the thumbnail to view the image.
The gas is stored approximately 1700 metres (circa 5,600 feet) below the surface. To put this into some sort of perspective, the towers on the Humber Bridge consist of a pair of hollow vertical concrete columns, each 155.5 metres (510 ft). Imagine, therefore, standing eleven columns on top of each other and that is the approximate depth of storage!